COSEE Releases Full-Process Tank Prefabrication Workflow and Quality Control Plan, Locking Acceptance Criteria to Nine Main Processes

2026-09-18

COSEE INDUSTRY SERVICE PTE LTD, or COSEE, has released its storage tank prefabrication workflow and quality control plan, which breaks tank prefabrication into nine main processes. For each one the plan sets out the inspection item, the applicable standard, the acceptance criteria and the record document to be retained, giving the shop floor a process control checklist it can apply directly.

The workflow begins at raw material receiving and then runs through welding preparation, cutting, bevel machining, sandblasting, forming, connection pipe welding and packaging up to final acceptance before dispatch. Cutting, for example, covers roof plates, shell plates, bottom plates and structural steel at the same time, with checks placed on nesting layout, the linear dimensions of cut pieces, cut edge quality and post-cutting piece numbering. To pass, the nesting scheme must already be approved, the quantity of plates and profiles must match the bill of quantities, and cut edges must carry no residual slag, deep notches or cracks.

Traceability at the source is where the workflow starts. Once steel arrives, the warehouse checks the delivery order against the mill's material certificates and completes a Raw Material Receiving Trace Log, recording heat number, material grade, size, quantity and MTR number item by item. A permanent mark is then left on the non-welding area of every plate, by steel stamping or a high-temperature marker pen, and only material that clears QC visual and dimensional inspection goes into storage; anything non-conforming is isolated with a rejection tag. In cutting, the technical nesting drawing has to show the original plate heat number behind each finished part, and a dedicated piece number is stamped or sprayed at a fixed position on the component body once blanking is done. Bevels are cold-machined on Shuangyou edge milling machines for X, Y and U grooves: before work starts, the process manager and the operator jointly confirm machine status and brief the job against the drawings, a diagram of the groove form is pasted onto each bevel edge, and trial cuts are taken with a small depth of cut and verified with an angle ruler and a straight ruler before machining formally begins.

Forming is governed by firm process discipline. Plates and profiles must be bent in line with their rolling direction, scale and foreign matter are cleared beforehand, and after forming the work is checked against a 2 m chord-length arc template with a gap to the surface of no more than 3 mm. The first plate of each specification is stood up and compared with the ground sample, and only a pass allows work to continue. Shot blasting and rust removal runs on a fully automatic steel shot pretreatment line reaching Sa2.5 cleanliness with a surface roughness of Rz 40-70 μm; it handles plate thicknesses of 5-158 mm, widths up to 5,000 mm and lengths up to 12,000 mm, with an annual capacity of 50,000-80,000 tons, and grooves and edges within a 100 mm range are shielded during blasting. For anti-corrosion painting, the coating must be uniform with no wrinkling, blistering, sagging or pinholes, and lifting lugs and connecting plates are coated at the same time.

Inspection and traceability run through every stage. Once connection pipes have been welded to flanges, fittings, manholes and similar items, PT, MT, RT or UT is performed to ASME SEC Ⅷ, with magnetic particle and penetrant testing reports for equipment and structural welds retained alongside. On-site testing tools are assigned by task: a tape measure for blanking dimensions, a multi-functional protractor for groove dimensions, a stainless steel template with a feeler gauge for arc roundness, a coating thickness gauge for film thickness, and an ultrasonic thickness gauge or micrometer for plate thickness. Marking control is equally strict - the number on the process transfer sheet must match the physical piece number, grinding and rolling may not erase the original permanent marks, and damaged marks are re-stamped on site. After coating is finished, a white permanent piece number is sprayed onto a non-stress area. At final factory acceptance, QC checks the physical number, the drawing and the traceability ledger part by part, and the packing list sets out every piece number together with its corresponding heat number.

Packaging and dispatch follow defined rules as well. Components are sorted by tank zone, shell course and priority, with outer and inner shells, dome and bottom plates kept separate and priority parts marked individually; coated surfaces take protective film and plate edges get soft padding. Curved components travel on custom arc-shaped steel frames with a load capacity of at least 32 tons and a stacking weight of 27-30 tons per frame, while plates are wrapped in moisture-proof paper and bound with steel strips spaced no more than 2.5 m apart. COSEE noted that the value of this workflow lies in fixing quality requirements into each individual process and record: the document package shipped with the goods covers material certificates, inspection reports for every process and complete traceability ledgers, so owners and third-party bodies can verify at any time.